Total Float in CPM evaluator uses Total Float = Latest Finish Time-Earliest Finish Time to evaluate the Total Float, The Total Float in CPM formula is defined as the time span by which the starting or finishing time can be delayed without delaying or affecting the overall project. The formula above is also valid as TF=LST-EST. Total Float is denoted by TF0 symbol.
How to evaluate Total Float in CPM using this online evaluator? To use this online evaluator for Total Float in CPM, enter Latest Finish Time (LFT) & Earliest Finish Time (EFT) and hit the calculate button.