Fx Copy
LaTeX Copy
Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Check FAQs
TF0=LFT-(EST+tactivity)
TF0 - Total Float?LFT - Late Finish Time?EST - Early Start Time?tactivity - Activity Time?

Total Float Example

With values
With units
Only example

Here is how the Total Float equation looks like with Values.

Here is how the Total Float equation looks like with Units.

Here is how the Total Float equation looks like.

18Edit=57Edit-(19Edit+20Edit)
You are here -
HomeIcon Home » Category Engineering » Category Mechanical » Category Industrial Engineering » fx Total Float

Total Float Solution

Follow our step by step solution on how to calculate Total Float?

FIRST Step Consider the formula
TF0=LFT-(EST+tactivity)
Next Step Substitute values of Variables
TF0=57d-(19d+20d)
Next Step Convert Units
TF0=4.9E+6s-(1.6E+6s+1.7E+6s)
Next Step Prepare to Evaluate
TF0=4.9E+6-(1.6E+6+1.7E+6)
Next Step Evaluate
TF0=1555200s
LAST Step Convert to Output's Unit
TF0=18d

Total Float Formula Elements

Variables
Total Float
Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date.
Symbol: TF0
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Late Finish Time
Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint.
Symbol: LFT
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Early Start Time
Early Start Time is the earliest point in time when the scheduled activity can begin.
Symbol: EST
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Activity Time
Activity time is the estimated task duration based on preceding logic and constraints.
Symbol: tactivity
Measurement: TimeUnit: d
Note: Value should be greater than 0.

Other Formulas to find Total Float

​Go Total Float given Start Time
TF0=LST-EST

Other formulas in Time Estimation category

​Go Early Finish Time
EFT=EST+S
​Go Expected Waiting Time for Customers in Queue
Wq=λaµ(µ-λa)
​Go Expected Waiting Time for Customers in System
Ws=1µ-λa
​Go Free Float
FF0=EFT-EST-tactivity

How to Evaluate Total Float?

Total Float evaluator uses Total Float = Late Finish Time-(Early Start Time+Activity Time) to evaluate the Total Float, Total float is the period by which an activity can shift its timing without affecting the relevant schedule completion date. Total Float is denoted by TF0 symbol.

How to evaluate Total Float using this online evaluator? To use this online evaluator for Total Float, enter Late Finish Time (LFT), Early Start Time (EST) & Activity Time (tactivity) and hit the calculate button.

FAQs on Total Float

What is the formula to find Total Float?
The formula of Total Float is expressed as Total Float = Late Finish Time-(Early Start Time+Activity Time). Here is an example- 0.000208 = 4924800-(1641600+1728000).
How to calculate Total Float?
With Late Finish Time (LFT), Early Start Time (EST) & Activity Time (tactivity) we can find Total Float using the formula - Total Float = Late Finish Time-(Early Start Time+Activity Time).
What are the other ways to Calculate Total Float?
Here are the different ways to Calculate Total Float-
  • Total Float=Late Start Time-Early Start TimeOpenImg
Can the Total Float be negative?
No, the Total Float, measured in Time cannot be negative.
Which unit is used to measure Total Float?
Total Float is usually measured using the Day[d] for Time. Second[d], Millisecond[d], Microsecond[d] are the few other units in which Total Float can be measured.
Copied!