Tool Positioning Time per Operation given Non-Productive Time in Turning Formula

Fx Copy
LaTeX Copy
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation. Check FAQs
tpt=NPT-(ts+NttstNb)-tlnn0
tpt - Tool Positioning Time Per Operation?NPT - Non-Productive Time?ts - Basic Setup Time?Nt - Number of Tools Used?tst - Setup Time Per Tool?Nb - Batch Size?tln - Loading And Unloading Time?n0 - Number of Operations?

Tool Positioning Time per Operation given Non-Productive Time in Turning Example

With values
With units
Only example

Here is how the Tool Positioning Time per Operation given Non-Productive Time in Turning equation looks like with Values.

Here is how the Tool Positioning Time per Operation given Non-Productive Time in Turning equation looks like with Units.

Here is how the Tool Positioning Time per Operation given Non-Productive Time in Turning equation looks like.

1.5005Edit=28.169Edit-(20.5Edit+4Edit10Edit3Edit)-30Edit5Edit
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Tool Positioning Time per Operation given Non-Productive Time in Turning

Tool Positioning Time per Operation given Non-Productive Time in Turning Solution

Follow our step by step solution on how to calculate Tool Positioning Time per Operation given Non-Productive Time in Turning?

FIRST Step Consider the formula
tpt=NPT-(ts+NttstNb)-tlnn0
Next Step Substitute values of Variables
tpt=28.169min-(20.5min+410min3)-30s5
Next Step Convert Units
tpt=1690.14s-(1230s+4600s3)-30s5
Next Step Prepare to Evaluate
tpt=1690.14-(1230+46003)-305
Next Step Evaluate
tpt=90.028s
Next Step Convert to Output's Unit
tpt=1.50046666666667min
LAST Step Rounding Answer
tpt=1.5005min

Tool Positioning Time per Operation given Non-Productive Time in Turning Formula Elements

Variables
Tool Positioning Time Per Operation
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Symbol: tpt
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Non-Productive Time
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Symbol: NPT
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Basic Setup Time
Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Setup Time Per Tool
Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Symbol: tst
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Loading And Unloading Time
Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Symbol: tln
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Number of Operations
The Number of Operations is defined as the total number of operations done in a batch.
Symbol: n0
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other formulas in Turning Operation category

​Go Diameter of Workpiece given Constant for Cylindrical Turning
d=KfπLcut
​Go Turning Length given Constant for Cylindrical Turning
Lcut=Kfπd

How to Evaluate Tool Positioning Time per Operation given Non-Productive Time in Turning?

Tool Positioning Time per Operation given Non-Productive Time in Turning evaluator uses Tool Positioning Time Per Operation = (Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-Loading And Unloading Time)/Number of Operations to evaluate the Tool Positioning Time Per Operation, The Tool Positioning Time per Operation given Non-Productive time in turning is defined as the time taken in changing and positioning the tool before the start of operation. Tool Positioning Time Per Operation is denoted by tpt symbol.

How to evaluate Tool Positioning Time per Operation given Non-Productive Time in Turning using this online evaluator? To use this online evaluator for Tool Positioning Time per Operation given Non-Productive Time in Turning, enter Non-Productive Time (NPT), Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Loading And Unloading Time (tln) & Number of Operations (n0) and hit the calculate button.

FAQs on Tool Positioning Time per Operation given Non-Productive Time in Turning

What is the formula to find Tool Positioning Time per Operation given Non-Productive Time in Turning?
The formula of Tool Positioning Time per Operation given Non-Productive Time in Turning is expressed as Tool Positioning Time Per Operation = (Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-Loading And Unloading Time)/Number of Operations. Here is an example- 0.025008 = (1690.14-((1230+4*600)/3)-30)/5.
How to calculate Tool Positioning Time per Operation given Non-Productive Time in Turning?
With Non-Productive Time (NPT), Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Loading And Unloading Time (tln) & Number of Operations (n0) we can find Tool Positioning Time per Operation given Non-Productive Time in Turning using the formula - Tool Positioning Time Per Operation = (Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-Loading And Unloading Time)/Number of Operations.
Can the Tool Positioning Time per Operation given Non-Productive Time in Turning be negative?
No, the Tool Positioning Time per Operation given Non-Productive Time in Turning, measured in Time cannot be negative.
Which unit is used to measure Tool Positioning Time per Operation given Non-Productive Time in Turning?
Tool Positioning Time per Operation given Non-Productive Time in Turning is usually measured using the Minute[min] for Time. Second[min], Millisecond[min], Microsecond[min] are the few other units in which Tool Positioning Time per Operation given Non-Productive Time in Turning can be measured.
Copied!