Time of Batch Leaching Operation Formula

Fx Copy
LaTeX Copy
The Time of Batch Leaching is the time the solid and the solvent is kept into contact (mixed together) in Batch Leaching Operation. Check FAQs
t=(-VLeachingAKL)ln((CS-CCS))
t - Time of Batch Leaching?VLeaching - Volume of Leaching Solution?A - Area of Leaching?KL - Mass Transfer Coefficient for Batch Leaching?CS - Concentration of Saturated Solution with Solute?C - Concentration of Solute in Bulk Solution at Time t?

Time of Batch Leaching Operation Example

With values
With units
Only example

Here is how the Time of Batch Leaching Operation equation looks like with Values.

Here is how the Time of Batch Leaching Operation equation looks like with Units.

Here is how the Time of Batch Leaching Operation equation looks like.

647.8416Edit=(-2.48Edit0.154Edit0.0147Edit)ln((56Edit-25Edit56Edit))
You are here -
HomeIcon Home » Category Engineering » Category Chemical Engineering » Category Mass Transfer Operations » fx Time of Batch Leaching Operation

Time of Batch Leaching Operation Solution

Follow our step by step solution on how to calculate Time of Batch Leaching Operation?

FIRST Step Consider the formula
t=(-VLeachingAKL)ln((CS-CCS))
Next Step Substitute values of Variables
t=(-2.480.1540.0147mol/s*m²)ln((56kg/m³-25kg/m³56kg/m³))
Next Step Prepare to Evaluate
t=(-2.480.1540.0147)ln((56-2556))
Next Step Evaluate
t=647.841649394826s
LAST Step Rounding Answer
t=647.8416s

Time of Batch Leaching Operation Formula Elements

Variables
Functions
Time of Batch Leaching
The Time of Batch Leaching is the time the solid and the solvent is kept into contact (mixed together) in Batch Leaching Operation.
Symbol: t
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Volume of Leaching Solution
The Volume of Leaching Solution is the volume of complete solution i.e. solute plus solvent for Leaching.
Symbol: VLeaching
Measurement: VolumeUnit:
Note: Value can be positive or negative.
Area of Leaching
The Area of Leaching is the are of contact available for leaching mass transfer, i.e. the surface area of the solids in contact with the solvent liquid.
Symbol: A
Measurement: AreaUnit:
Note: Value should be greater than 0.
Mass Transfer Coefficient for Batch Leaching
The Mass Transfer Coefficient for Batch Leaching is the coefficient that accounts for driving force for mass transfer in the liquid phase.
Symbol: KL
Measurement: Molar Flux of Diffusing ComponentUnit: mol/s*m²
Note: Value should be greater than 0.
Concentration of Saturated Solution with Solute
The Concentration of Saturated Solution with Solute is the concentration of the saturated solution in contact with the solute particles for batch leaching process.
Symbol: CS
Measurement: Mass ConcentrationUnit: kg/m³
Note: Value should be greater than 0.
Concentration of Solute in Bulk Solution at Time t
The Concentration of Solute in Bulk Solution at Time t is the solute concentration in bulk of solution at time t of the batch leaching process.
Symbol: C
Measurement: Mass ConcentrationUnit: kg/m³
Note: Value should be greater than 0.
ln
The natural logarithm, also known as the logarithm to the base e, is the inverse function of the natural exponential function.
Syntax: ln(Number)

Other formulas in Operation category

​Go Area of Contact for Batch Leaching Operation
A=(-VLeachingKLt)ln((CS-CCS))
​Go Concentration of Solute in Bulk Solution at Time t for Batch Leaching
C=CS(1-exp(-KLAtVLeaching))
​Go Volume of Leaching Solution in Batch Leaching
VLeaching=-KLAtln((CS-CCS))
​Go Beta Value based on Ratio of Solvent
β=ba

How to Evaluate Time of Batch Leaching Operation?

Time of Batch Leaching Operation evaluator uses Time of Batch Leaching = (-Volume of Leaching Solution/(Area of Leaching*Mass Transfer Coefficient for Batch Leaching))*ln(((Concentration of Saturated Solution with Solute-Concentration of Solute in Bulk Solution at Time t)/Concentration of Saturated Solution with Solute)) to evaluate the Time of Batch Leaching, The Time of Batch Leaching Operation formula is defined as the Time of contact between the solid particles and the solvent in the batch leaching operation, also commonly considered as the time of agitation of the solution. Time of Batch Leaching is denoted by t symbol.

How to evaluate Time of Batch Leaching Operation using this online evaluator? To use this online evaluator for Time of Batch Leaching Operation, enter Volume of Leaching Solution (VLeaching), Area of Leaching (A), Mass Transfer Coefficient for Batch Leaching (KL), Concentration of Saturated Solution with Solute (CS) & Concentration of Solute in Bulk Solution at Time t (C) and hit the calculate button.

FAQs on Time of Batch Leaching Operation

What is the formula to find Time of Batch Leaching Operation?
The formula of Time of Batch Leaching Operation is expressed as Time of Batch Leaching = (-Volume of Leaching Solution/(Area of Leaching*Mass Transfer Coefficient for Batch Leaching))*ln(((Concentration of Saturated Solution with Solute-Concentration of Solute in Bulk Solution at Time t)/Concentration of Saturated Solution with Solute)). Here is an example- 647.8416 = (-2.48/(0.154*0.0147))*ln(((56-25)/56)).
How to calculate Time of Batch Leaching Operation?
With Volume of Leaching Solution (VLeaching), Area of Leaching (A), Mass Transfer Coefficient for Batch Leaching (KL), Concentration of Saturated Solution with Solute (CS) & Concentration of Solute in Bulk Solution at Time t (C) we can find Time of Batch Leaching Operation using the formula - Time of Batch Leaching = (-Volume of Leaching Solution/(Area of Leaching*Mass Transfer Coefficient for Batch Leaching))*ln(((Concentration of Saturated Solution with Solute-Concentration of Solute in Bulk Solution at Time t)/Concentration of Saturated Solution with Solute)). This formula also uses Natural Logarithm Function function(s).
Can the Time of Batch Leaching Operation be negative?
No, the Time of Batch Leaching Operation, measured in Time cannot be negative.
Which unit is used to measure Time of Batch Leaching Operation?
Time of Batch Leaching Operation is usually measured using the Second[s] for Time. Millisecond[s], Microsecond[s], Nanosecond[s] are the few other units in which Time of Batch Leaching Operation can be measured.
Copied!