Scraper Cycle Time given Number of Scrapers Pusher can Load Formula

Fx Copy
LaTeX Copy
Scraper Cycle Time is estimated by adding the fixed times to load, dumps, and turn around. Check FAQs
Ts=(NpTp)
Ts - Scraper Cycle Time?Np - Number of Scraper a Pusher?Tp - Pusher Cycle Time?

Scraper Cycle Time given Number of Scrapers Pusher can Load Example

With values
With units
Only example

Here is how the Scraper Cycle Time given Number of Scrapers Pusher can Load equation looks like with Values.

Here is how the Scraper Cycle Time given Number of Scrapers Pusher can Load equation looks like with Units.

Here is how the Scraper Cycle Time given Number of Scrapers Pusher can Load equation looks like.

36.12Edit=(12Edit3.01Edit)
You are here -
HomeIcon Home » Category Engineering » Category Civil » Category Geotechnical Engineering » fx Scraper Cycle Time given Number of Scrapers Pusher can Load

Scraper Cycle Time given Number of Scrapers Pusher can Load Solution

Follow our step by step solution on how to calculate Scraper Cycle Time given Number of Scrapers Pusher can Load?

FIRST Step Consider the formula
Ts=(NpTp)
Next Step Substitute values of Variables
Ts=(123.01min)
Next Step Convert Units
Ts=(12180.6s)
Next Step Prepare to Evaluate
Ts=(12180.6)
Next Step Evaluate
Ts=2167.2s
LAST Step Convert to Output's Unit
Ts=36.12min

Scraper Cycle Time given Number of Scrapers Pusher can Load Formula Elements

Variables
Scraper Cycle Time
Scraper Cycle Time is estimated by adding the fixed times to load, dumps, and turn around.
Symbol: Ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Scraper a Pusher
Number of Scraper a Pusher can load calculates the scraper number when scraper and pusher cycle time is known.
Symbol: Np
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Pusher Cycle Time
Pusher Cycle Time consists of maneuver time and load time.
Symbol: Tp
Measurement: TimeUnit: min
Note: Value should be greater than 0.

Other formulas in Scraper Production category

​Go Production of Scrap by Machines
Ps=(Lf)
​Go Load Given Production of Scrap by Machines
L=(Psf)
​Go Trips per Hour given Production of Scrap by Machines
f=(PsL)
​Go Trips per Hour for Excavating Scrap
f=(WTCt)

How to Evaluate Scraper Cycle Time given Number of Scrapers Pusher can Load?

Scraper Cycle Time given Number of Scrapers Pusher can Load evaluator uses Scraper Cycle Time = (Number of Scraper a Pusher*Pusher Cycle Time) to evaluate the Scraper Cycle Time, The Scraper Cycle Time given Number of Scrapers Pusher can Load is defined as the time required by the scraper in completing one cycle of work. Scraper Cycle Time is denoted by Ts symbol.

How to evaluate Scraper Cycle Time given Number of Scrapers Pusher can Load using this online evaluator? To use this online evaluator for Scraper Cycle Time given Number of Scrapers Pusher can Load, enter Number of Scraper a Pusher (Np) & Pusher Cycle Time (Tp) and hit the calculate button.

FAQs on Scraper Cycle Time given Number of Scrapers Pusher can Load

What is the formula to find Scraper Cycle Time given Number of Scrapers Pusher can Load?
The formula of Scraper Cycle Time given Number of Scrapers Pusher can Load is expressed as Scraper Cycle Time = (Number of Scraper a Pusher*Pusher Cycle Time). Here is an example- 0.6 = (12*180.6).
How to calculate Scraper Cycle Time given Number of Scrapers Pusher can Load?
With Number of Scraper a Pusher (Np) & Pusher Cycle Time (Tp) we can find Scraper Cycle Time given Number of Scrapers Pusher can Load using the formula - Scraper Cycle Time = (Number of Scraper a Pusher*Pusher Cycle Time).
Can the Scraper Cycle Time given Number of Scrapers Pusher can Load be negative?
No, the Scraper Cycle Time given Number of Scrapers Pusher can Load, measured in Time cannot be negative.
Which unit is used to measure Scraper Cycle Time given Number of Scrapers Pusher can Load?
Scraper Cycle Time given Number of Scrapers Pusher can Load is usually measured using the Minute[min] for Time. Second[min], Millisecond[min], Microsecond[min] are the few other units in which Scraper Cycle Time given Number of Scrapers Pusher can Load can be measured.
Copied!