Pusher Cycle Time given Number of Scrapers Pusher can Load Formula

Fx Copy
LaTeX Copy
Pusher Cycle Time consists of maneuver time and load time. Check FAQs
Tp=(TsNp)
Tp - Pusher Cycle Time?Ts - Scraper Cycle Time?Np - Number of Scraper a Pusher?

Pusher Cycle Time given Number of Scrapers Pusher can Load Example

With values
With units
Only example

Here is how the Pusher Cycle Time given Number of Scrapers Pusher can Load equation looks like with Values.

Here is how the Pusher Cycle Time given Number of Scrapers Pusher can Load equation looks like with Units.

Here is how the Pusher Cycle Time given Number of Scrapers Pusher can Load equation looks like.

0.6Edit=(7.2Edit12Edit)
You are here -
HomeIcon Home » Category Engineering » Category Civil » Category Geotechnical Engineering » fx Pusher Cycle Time given Number of Scrapers Pusher can Load

Pusher Cycle Time given Number of Scrapers Pusher can Load Solution

Follow our step by step solution on how to calculate Pusher Cycle Time given Number of Scrapers Pusher can Load?

FIRST Step Consider the formula
Tp=(TsNp)
Next Step Substitute values of Variables
Tp=(7.2min12)
Next Step Convert Units
Tp=(432s12)
Next Step Prepare to Evaluate
Tp=(43212)
Next Step Evaluate
Tp=36s
LAST Step Convert to Output's Unit
Tp=0.6min

Pusher Cycle Time given Number of Scrapers Pusher can Load Formula Elements

Variables
Pusher Cycle Time
Pusher Cycle Time consists of maneuver time and load time.
Symbol: Tp
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Scraper Cycle Time
Scraper Cycle Time is estimated by adding the fixed times to load, dumps, and turn around.
Symbol: Ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Scraper a Pusher
Number of Scraper a Pusher can load calculates the scraper number when scraper and pusher cycle time is known.
Symbol: Np
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other formulas in Scraper Production category

​Go Production of Scrap by Machines
Ps=(Lf)
​Go Load Given Production of Scrap by Machines
L=(Psf)
​Go Trips per Hour given Production of Scrap by Machines
f=(PsL)
​Go Trips per Hour for Excavating Scrap
f=(WTCt)

How to Evaluate Pusher Cycle Time given Number of Scrapers Pusher can Load?

Pusher Cycle Time given Number of Scrapers Pusher can Load evaluator uses Pusher Cycle Time = (Scraper Cycle Time/Number of Scraper a Pusher) to evaluate the Pusher Cycle Time, The Pusher Cycle Time given Number of Scrapers Pusher can Load is defined as the time required by the pusher. Pusher Cycle Time is denoted by Tp symbol.

How to evaluate Pusher Cycle Time given Number of Scrapers Pusher can Load using this online evaluator? To use this online evaluator for Pusher Cycle Time given Number of Scrapers Pusher can Load, enter Scraper Cycle Time (Ts) & Number of Scraper a Pusher (Np) and hit the calculate button.

FAQs on Pusher Cycle Time given Number of Scrapers Pusher can Load

What is the formula to find Pusher Cycle Time given Number of Scrapers Pusher can Load?
The formula of Pusher Cycle Time given Number of Scrapers Pusher can Load is expressed as Pusher Cycle Time = (Scraper Cycle Time/Number of Scraper a Pusher). Here is an example- 0.01 = (432/12).
How to calculate Pusher Cycle Time given Number of Scrapers Pusher can Load?
With Scraper Cycle Time (Ts) & Number of Scraper a Pusher (Np) we can find Pusher Cycle Time given Number of Scrapers Pusher can Load using the formula - Pusher Cycle Time = (Scraper Cycle Time/Number of Scraper a Pusher).
Can the Pusher Cycle Time given Number of Scrapers Pusher can Load be negative?
No, the Pusher Cycle Time given Number of Scrapers Pusher can Load, measured in Time cannot be negative.
Which unit is used to measure Pusher Cycle Time given Number of Scrapers Pusher can Load?
Pusher Cycle Time given Number of Scrapers Pusher can Load is usually measured using the Minute[min] for Time. Second[min], Millisecond[min], Microsecond[min] are the few other units in which Pusher Cycle Time given Number of Scrapers Pusher can Load can be measured.
Copied!