PERT Expected Time evaluator uses PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6 to evaluate the PERT Expected Time, PERT expected time is a method of calculating project completion times both for your own scheduling and for your customers' needs. PERT Expected Time is denoted by te symbol.
How to evaluate PERT Expected Time using this online evaluator? To use this online evaluator for PERT Expected Time, enter Optimistic Time (Toptimistic), Most Likely Time (tm) & Pessimistic Time (TPessimistic) and hit the calculate button.