PERT Expected Time Formula

Fx Copy
LaTeX Copy
PERT Expected Time is a method of calculating project completion times both for your own scheduling and for your customers' needs. Check FAQs
te=Toptimistic+4tm+TPessimistic6
te - PERT Expected Time?Toptimistic - Optimistic Time?tm - Most Likely Time?TPessimistic - Pessimistic Time?

PERT Expected Time Example

With values
With units
Only example

Here is how the PERT Expected Time equation looks like with Values.

Here is how the PERT Expected Time equation looks like with Units.

Here is how the PERT Expected Time equation looks like.

11.8333Edit=9Edit+413Edit+10Edit6
You are here -
HomeIcon Home » Category Engineering » Category Mechanical » Category Industrial Engineering » fx PERT Expected Time

PERT Expected Time Solution

Follow our step by step solution on how to calculate PERT Expected Time?

FIRST Step Consider the formula
te=Toptimistic+4tm+TPessimistic6
Next Step Substitute values of Variables
te=9d+413d+10d6
Next Step Convert Units
te=777600s+41.1E+6s+864000s6
Next Step Prepare to Evaluate
te=777600+41.1E+6+8640006
Next Step Evaluate
te=1022400s
Next Step Convert to Output's Unit
te=11.8333333333333d
LAST Step Rounding Answer
te=11.8333d

PERT Expected Time Formula Elements

Variables
PERT Expected Time
PERT Expected Time is a method of calculating project completion times both for your own scheduling and for your customers' needs.
Symbol: te
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Optimistic Time
Optimistic Time is the shortest possible time to complete the activity if all goes well.
Symbol: Toptimistic
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Most Likely Time
Most Likely Time is the normal time activity would take.
Symbol: tm
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Pessimistic Time
A pessimistic Time is the longest time that an activity could take if everything is wrong.
Symbol: TPessimistic
Measurement: TimeUnit: d
Note: Value should be greater than 0.

Other formulas in Time Estimation category

​Go Early Finish Time
EFT=EST+S
​Go Expected Waiting Time for Customers in Queue
Wq=λaµ(µ-λa)
​Go Expected Waiting Time for Customers in System
Ws=1µ-λa
​Go Free Float
FF0=EFT-EST-tactivity

How to Evaluate PERT Expected Time?

PERT Expected Time evaluator uses PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6 to evaluate the PERT Expected Time, PERT expected time is a method of calculating project completion times both for your own scheduling and for your customers' needs. PERT Expected Time is denoted by te symbol.

How to evaluate PERT Expected Time using this online evaluator? To use this online evaluator for PERT Expected Time, enter Optimistic Time (Toptimistic), Most Likely Time (tm) & Pessimistic Time (TPessimistic) and hit the calculate button.

FAQs on PERT Expected Time

What is the formula to find PERT Expected Time?
The formula of PERT Expected Time is expressed as PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6. Here is an example- 0.000137 = (777600+4*1123200+864000)/6.
How to calculate PERT Expected Time?
With Optimistic Time (Toptimistic), Most Likely Time (tm) & Pessimistic Time (TPessimistic) we can find PERT Expected Time using the formula - PERT Expected Time = (Optimistic Time+4*Most Likely Time+Pessimistic Time)/6.
Can the PERT Expected Time be negative?
No, the PERT Expected Time, measured in Time cannot be negative.
Which unit is used to measure PERT Expected Time?
PERT Expected Time is usually measured using the Day[d] for Time. Second[d], Millisecond[d], Microsecond[d] are the few other units in which PERT Expected Time can be measured.
Copied!