Non-Productive Time in Turning Formula

Fx Copy
LaTeX Copy
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts. Check FAQs
NPT=(ts+NttstNb)+tln+(tptn0)
NPT - Non-Productive Time?ts - Basic Setup Time?Nt - Number of Tools Used?tst - Setup Time Per Tool?Nb - Batch Size?tln - Loading And Unloading Time?tpt - Tool Positioning Time Per Operation?n0 - Number of Operations?

Non-Productive Time in Turning Example

With values
With units
Only example

Here is how the Non-Productive Time in Turning equation looks like with Values.

Here is how the Non-Productive Time in Turning equation looks like with Units.

Here is how the Non-Productive Time in Turning equation looks like.

28.1667Edit=(20.5Edit+4Edit10Edit3Edit)+30Edit+(1.5Edit5Edit)
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Non-Productive Time in Turning

Non-Productive Time in Turning Solution

Follow our step by step solution on how to calculate Non-Productive Time in Turning?

FIRST Step Consider the formula
NPT=(ts+NttstNb)+tln+(tptn0)
Next Step Substitute values of Variables
NPT=(20.5min+410min3)+30s+(1.5min5)
Next Step Convert Units
NPT=(1230s+4600s3)+30s+(90s5)
Next Step Prepare to Evaluate
NPT=(1230+46003)+30+(905)
Next Step Evaluate
NPT=1690s
Next Step Convert to Output's Unit
NPT=28.1666666666667min
LAST Step Rounding Answer
NPT=28.1667min

Non-Productive Time in Turning Formula Elements

Variables
Non-Productive Time
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Symbol: NPT
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Basic Setup Time
Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Setup Time Per Tool
Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Symbol: tst
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Loading And Unloading Time
Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Symbol: tln
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Tool Positioning Time Per Operation
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Symbol: tpt
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Operations
The Number of Operations is defined as the total number of operations done in a batch.
Symbol: n0
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other formulas in Turning Operation category

​Go Diameter of Workpiece given Constant for Cylindrical Turning
d=KfπLcut
​Go Turning Length given Constant for Cylindrical Turning
Lcut=Kfπd

How to Evaluate Non-Productive Time in Turning?

Non-Productive Time in Turning evaluator uses Non-Productive Time = ((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)+Loading And Unloading Time+(Tool Positioning Time Per Operation*Number of Operations) to evaluate the Non-Productive Time, The Non-Productive Time in Turning is the total time wasted in setting up the machine or workpiece for a particular process. Non-Productive Time is denoted by NPT symbol.

How to evaluate Non-Productive Time in Turning using this online evaluator? To use this online evaluator for Non-Productive Time in Turning, enter Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) and hit the calculate button.

FAQs on Non-Productive Time in Turning

What is the formula to find Non-Productive Time in Turning?
The formula of Non-Productive Time in Turning is expressed as Non-Productive Time = ((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)+Loading And Unloading Time+(Tool Positioning Time Per Operation*Number of Operations). Here is an example- 0.469444 = ((1230+4*600)/3)+30+(90*5).
How to calculate Non-Productive Time in Turning?
With Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) we can find Non-Productive Time in Turning using the formula - Non-Productive Time = ((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)+Loading And Unloading Time+(Tool Positioning Time Per Operation*Number of Operations).
Can the Non-Productive Time in Turning be negative?
No, the Non-Productive Time in Turning, measured in Time cannot be negative.
Which unit is used to measure Non-Productive Time in Turning?
Non-Productive Time in Turning is usually measured using the Minute[min] for Time. Second[min], Millisecond[min], Microsecond[min] are the few other units in which Non-Productive Time in Turning can be measured.