Maximum Quantity of Steel is the maximum mass of steel in kg that we will be requiring in the construction of a particular RCC component. Check FAQs
Qsteel=0.008NocolumnsVfoundationρsteel
Qsteel - Maximum Quantity of Steel?Nocolumns - Number of Columns?Vfoundation - Volume of Foundation?ρsteel - Density of Steel?

Maximum Steel Quantity Estimation for Foundations Example

With values
With units
Only example

Here is how the Maximum Steel Quantity Estimation for Foundations equation looks like with Values.

Here is how the Maximum Steel Quantity Estimation for Foundations equation looks like with Units.

Here is how the Maximum Steel Quantity Estimation for Foundations equation looks like.

1448.7552Edit=0.00812Edit1.92Edit7860Edit
You are here -
HomeIcon Home » Category Engineering » Category Civil » Category Estimation and Costing » fx Maximum Steel Quantity Estimation for Foundations

Maximum Steel Quantity Estimation for Foundations Solution

Follow our step by step solution on how to calculate Maximum Steel Quantity Estimation for Foundations?

FIRST Step Consider the formula
Qsteel=0.008NocolumnsVfoundationρsteel
Next Step Substitute values of Variables
Qsteel=0.008121.927860kg/m³
Next Step Prepare to Evaluate
Qsteel=0.008121.927860
LAST Step Evaluate
Qsteel=1448.7552kg

Maximum Steel Quantity Estimation for Foundations Formula Elements

Variables
Maximum Quantity of Steel
Maximum Quantity of Steel is the maximum mass of steel in kg that we will be requiring in the construction of a particular RCC component.
Symbol: Qsteel
Measurement: WeightUnit: kg
Note: Value should be greater than 0.
Number of Columns
Number of Columns defines the total number of RCC beams in the structure of a given specification.
Symbol: Nocolumns
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Volume of Foundation
Volume of foundation is obtained by multiplying length of the footing X Width of the footing X Depth of the footing.
Symbol: Vfoundation
Measurement: VolumeUnit:
Note: Value should be greater than 0.
Density of Steel
Density of steel is usually taken as 7860kg/m3 in civil domain. Though there exists steel of different densities Carbon steel's density is about 7.84 g/cm3,stainless steel's is about 8.03 g/cm3.
Symbol: ρsteel
Measurement: DensityUnit: kg/m³
Note: Value should be greater than 0.

Other Formulas to find Maximum Quantity of Steel

​Go Maximum Steel Quantity Estimation for Beams
Qsteel=0.02NobeamsVbeamρsteel
​Go Maximum Steel Quantity Estimation for Columns
Qsteel=0.06NocolumnsVcolumnρsteel
​Go Maximum Steel Quantity Estimation for RCC Slab
Qsteel=0.015Aslabtslabρsteel

How to Evaluate Maximum Steel Quantity Estimation for Foundations?

Maximum Steel Quantity Estimation for Foundations evaluator uses Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel to evaluate the Maximum Quantity of Steel, The Maximum Steel Quantity Estimation for Foundations formula is defined as calculating the amount of steel in kgs that will be required for foundations of a given number of foundations having the same specifications in the structure. Here, the volume of the foundation =length of the footing X width of the footing X depth of the footing. Maximum Quantity of Steel is denoted by Qsteel symbol.

How to evaluate Maximum Steel Quantity Estimation for Foundations using this online evaluator? To use this online evaluator for Maximum Steel Quantity Estimation for Foundations, enter Number of Columns (Nocolumns), Volume of Foundation (Vfoundation) & Density of Steel steel) and hit the calculate button.

FAQs on Maximum Steel Quantity Estimation for Foundations

What is the formula to find Maximum Steel Quantity Estimation for Foundations?
The formula of Maximum Steel Quantity Estimation for Foundations is expressed as Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel. Here is an example- 1448.755 = 0.008*12*1.92*7860.
How to calculate Maximum Steel Quantity Estimation for Foundations?
With Number of Columns (Nocolumns), Volume of Foundation (Vfoundation) & Density of Steel steel) we can find Maximum Steel Quantity Estimation for Foundations using the formula - Maximum Quantity of Steel = 0.008*Number of Columns*Volume of Foundation*Density of Steel.
What are the other ways to Calculate Maximum Quantity of Steel?
Here are the different ways to Calculate Maximum Quantity of Steel-
  • Maximum Quantity of Steel=0.02*Number of Beams*Volume of Beam*Density of SteelOpenImg
  • Maximum Quantity of Steel=0.06*Number of Columns*Volume of Columns*Density of SteelOpenImg
  • Maximum Quantity of Steel=0.015*Area of Slab*Thickness of Slab*Density of SteelOpenImg
Can the Maximum Steel Quantity Estimation for Foundations be negative?
No, the Maximum Steel Quantity Estimation for Foundations, measured in Weight cannot be negative.
Which unit is used to measure Maximum Steel Quantity Estimation for Foundations?
Maximum Steel Quantity Estimation for Foundations is usually measured using the Kilogram[kg] for Weight. Gram[kg], Milligram[kg], Ton (Metric)[kg] are the few other units in which Maximum Steel Quantity Estimation for Foundations can be measured.
Copied!