Maximum Demand is defined as the peak power consumption of the load connected. Check FAQs
Max Demand=Avg LoadLoad Factor
Max Demand - Maximum Demand?Avg Load - Average Load?Load Factor - Load Factor?

Maximum Demand given Load Factor Example

With values
With units
Only example

Here is how the Maximum Demand given Load Factor equation looks like with Values.

Here is how the Maximum Demand given Load Factor equation looks like with Units.

Here is how the Maximum Demand given Load Factor equation looks like.

1700Edit=1105Edit0.65Edit
You are here -
HomeIcon Home » Category Engineering » Category Electrical » Category Power Plant Operations » fx Maximum Demand given Load Factor

Maximum Demand given Load Factor Solution

Follow our step by step solution on how to calculate Maximum Demand given Load Factor?

FIRST Step Consider the formula
Max Demand=Avg LoadLoad Factor
Next Step Substitute values of Variables
Max Demand=1105kW0.65
Next Step Convert Units
Max Demand=1.1E+6W0.65
Next Step Prepare to Evaluate
Max Demand=1.1E+60.65
Next Step Evaluate
Max Demand=1700000W
LAST Step Convert to Output's Unit
Max Demand=1700kW

Maximum Demand given Load Factor Formula Elements

Variables
Maximum Demand
Maximum Demand is defined as the peak power consumption of the load connected.
Symbol: Max Demand
Measurement: PowerUnit: kW
Note: Value should be greater than 0.
Average Load
Average Load is the average load occurring on the power station in a given period known as an average load.
Symbol: Avg Load
Measurement: PowerUnit: kW
Note: Value should be greater than 0.
Load Factor
Load Factor is the ratio of average load to the maximum demand during a given period.
Symbol: Load Factor
Measurement: NAUnit: Unitless
Note: Value should be less than 1.0001.

Other Formulas to find Maximum Demand

​Go Maximum Demand using Demand Factor
Max Demand=Demand FactorConnected Load

Other formulas in Power Plant Operational Factors category

​Go Average Load for Load Curve
Avg Load=AL24
​Go Load Factor given Average Load and Maximum Demand
Load Factor=Avg LoadMax Demand
​Go Unit Generated per Annum
Pg=Max DemandLoad Factor8760
​Go Demand Factor
Demand Factor=Max DemandConnected Load

How to Evaluate Maximum Demand given Load Factor?

Maximum Demand given Load Factor evaluator uses Maximum Demand = Average Load/Load Factor to evaluate the Maximum Demand, Maximum Demand given Load Factor is defined as the maximum raise in demand. It is generally measured in MW. Maximum Demand is denoted by Max Demand symbol.

How to evaluate Maximum Demand given Load Factor using this online evaluator? To use this online evaluator for Maximum Demand given Load Factor, enter Average Load (Avg Load) & Load Factor (Load Factor) and hit the calculate button.

FAQs on Maximum Demand given Load Factor

What is the formula to find Maximum Demand given Load Factor?
The formula of Maximum Demand given Load Factor is expressed as Maximum Demand = Average Load/Load Factor. Here is an example- 1.7 = 1105000/0.65.
How to calculate Maximum Demand given Load Factor?
With Average Load (Avg Load) & Load Factor (Load Factor) we can find Maximum Demand given Load Factor using the formula - Maximum Demand = Average Load/Load Factor.
What are the other ways to Calculate Maximum Demand?
Here are the different ways to Calculate Maximum Demand-
  • Maximum Demand=Demand Factor*Connected LoadOpenImg
Can the Maximum Demand given Load Factor be negative?
No, the Maximum Demand given Load Factor, measured in Power cannot be negative.
Which unit is used to measure Maximum Demand given Load Factor?
Maximum Demand given Load Factor is usually measured using the Kilowatt[kW] for Power. Watt[kW], Milliwatt[kW], Microwatt[kW] are the few other units in which Maximum Demand given Load Factor can be measured.