Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation. Check FAQs
tln=NPT-(ts+NttstNb)-(tptn0)
tln - Loading And Unloading Time?NPT - Non-Productive Time?ts - Basic Setup Time?Nt - Number of Tools Used?tst - Setup Time Per Tool?Nb - Batch Size?tpt - Tool Positioning Time Per Operation?n0 - Number of Operations?

Loading and Unloading Time given Non-productive Time in Turning Example

With values
With units
Only example

Here is how the Loading and Unloading Time given Non-productive Time in Turning equation looks like with Values.

Here is how the Loading and Unloading Time given Non-productive Time in Turning equation looks like with Units.

Here is how the Loading and Unloading Time given Non-productive Time in Turning equation looks like.

30.14Edit=28.169Edit-(20.5Edit+4Edit10Edit3Edit)-(1.5Edit5Edit)
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Loading and Unloading Time given Non-productive Time in Turning

Loading and Unloading Time given Non-productive Time in Turning Solution

Follow our step by step solution on how to calculate Loading and Unloading Time given Non-productive Time in Turning?

FIRST Step Consider the formula
tln=NPT-(ts+NttstNb)-(tptn0)
Next Step Substitute values of Variables
tln=28.169min-(20.5min+410min3)-(1.5min5)
Next Step Convert Units
tln=1690.14s-(1230s+4600s3)-(90s5)
Next Step Prepare to Evaluate
tln=1690.14-(1230+46003)-(905)
Next Step Evaluate
tln=30.1400000000001s
LAST Step Rounding Answer
tln=30.14s

Loading and Unloading Time given Non-productive Time in Turning Formula Elements

Variables
Loading And Unloading Time
Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Symbol: tln
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Non-Productive Time
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Symbol: NPT
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Basic Setup Time
Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Setup Time Per Tool
Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Symbol: tst
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Tool Positioning Time Per Operation
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Symbol: tpt
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Operations
The Number of Operations is defined as the total number of operations done in a batch.
Symbol: n0
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other formulas in Turning Operation category

​Go Diameter of Workpiece given Constant for Cylindrical Turning
d=KfπLcut
​Go Turning Length given Constant for Cylindrical Turning
Lcut=Kfπd

How to Evaluate Loading and Unloading Time given Non-productive Time in Turning?

Loading and Unloading Time given Non-productive Time in Turning evaluator uses Loading And Unloading Time = Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-(Tool Positioning Time Per Operation*Number of Operations) to evaluate the Loading And Unloading Time, The Loading and Unloading Time given Non-productive Time in Turning is the time required to load/unload the workpiece before the start of machine operation. Loading And Unloading Time is denoted by tln symbol.

How to evaluate Loading and Unloading Time given Non-productive Time in Turning using this online evaluator? To use this online evaluator for Loading and Unloading Time given Non-productive Time in Turning, enter Non-Productive Time (NPT), Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) and hit the calculate button.

FAQs on Loading and Unloading Time given Non-productive Time in Turning

What is the formula to find Loading and Unloading Time given Non-productive Time in Turning?
The formula of Loading and Unloading Time given Non-productive Time in Turning is expressed as Loading And Unloading Time = Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-(Tool Positioning Time Per Operation*Number of Operations). Here is an example- 0.008372 = 1690.14-((1230+4*600)/3)-(90*5).
How to calculate Loading and Unloading Time given Non-productive Time in Turning?
With Non-Productive Time (NPT), Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Batch Size (Nb), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) we can find Loading and Unloading Time given Non-productive Time in Turning using the formula - Loading And Unloading Time = Non-Productive Time-((Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/Batch Size)-(Tool Positioning Time Per Operation*Number of Operations).
Can the Loading and Unloading Time given Non-productive Time in Turning be negative?
No, the Loading and Unloading Time given Non-productive Time in Turning, measured in Time cannot be negative.
Which unit is used to measure Loading and Unloading Time given Non-productive Time in Turning?
Loading and Unloading Time given Non-productive Time in Turning is usually measured using the Second[s] for Time. Millisecond[s], Microsecond[s], Nanosecond[s] are the few other units in which Loading and Unloading Time given Non-productive Time in Turning can be measured.
Copied!