Loaded Volume is the volume of soil after excavation. Check FAQs
VL=(VO100+0.01s100)
VL - Loaded Volume?VO - Original volume of Soil?s - Swell in Soil?

Loaded Volume of Soil given Percent Swell Example

With values
With units
Only example

Here is how the Loaded Volume of Soil given Percent Swell equation looks like with Values.

Here is how the Loaded Volume of Soil given Percent Swell equation looks like with Units.

Here is how the Loaded Volume of Soil given Percent Swell equation looks like.

22.011Edit=(22Edit100+0.015Edit100)
You are here -
HomeIcon Home » Category Engineering » Category Civil » Category Geotechnical Engineering » fx Loaded Volume of Soil given Percent Swell

Loaded Volume of Soil given Percent Swell Solution

Follow our step by step solution on how to calculate Loaded Volume of Soil given Percent Swell?

FIRST Step Consider the formula
VL=(VO100+0.01s100)
Next Step Substitute values of Variables
VL=(22100+0.015100)
Next Step Prepare to Evaluate
VL=(22100+0.015100)
LAST Step Evaluate
VL=22.011

Loaded Volume of Soil given Percent Swell Formula Elements

Variables
Loaded Volume
Loaded Volume is the volume of soil after excavation.
Symbol: VL
Measurement: VolumeUnit:
Note: Value should be greater than 0.
Original volume of Soil
Original volume of Soil is the volume of soil before excavation.
Symbol: VO
Measurement: VolumeUnit:
Note: Value should be greater than 0.
Swell in Soil
Swell in Soil is change in volume when subjected to moisture.
Symbol: s
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other Formulas to find Loaded Volume

​Go Loaded Volume of Soil given Original Volume of Soil
VL=(VOLF)

Other formulas in Earth Quantities Hauled category

​Go Original Volume of Soil before Excavation
VO=VLLF
​Go Load Factor given Original Volume of Soil
LF=(VOVL)
​Go Original Volume of Soil before Excavation given Percent Swell
VO=(100100+0.01s)VL
​Go Swell in Soil given Original Volume of Soil
s'=10000((VLVO)-1)

How to Evaluate Loaded Volume of Soil given Percent Swell?

Loaded Volume of Soil given Percent Swell evaluator uses Loaded Volume = (Original volume of Soil*(100+0.01*Swell in Soil)/100) to evaluate the Loaded Volume, The Loaded Volume of Soil given Percent Swell formula is defined as the volume of soil after the excavation and loading of soil. Loaded Volume is denoted by VL symbol.

How to evaluate Loaded Volume of Soil given Percent Swell using this online evaluator? To use this online evaluator for Loaded Volume of Soil given Percent Swell, enter Original volume of Soil (VO) & Swell in Soil (s) and hit the calculate button.

FAQs on Loaded Volume of Soil given Percent Swell

What is the formula to find Loaded Volume of Soil given Percent Swell?
The formula of Loaded Volume of Soil given Percent Swell is expressed as Loaded Volume = (Original volume of Soil*(100+0.01*Swell in Soil)/100). Here is an example- 20.01 = (22*(100+0.01*5)/100).
How to calculate Loaded Volume of Soil given Percent Swell?
With Original volume of Soil (VO) & Swell in Soil (s) we can find Loaded Volume of Soil given Percent Swell using the formula - Loaded Volume = (Original volume of Soil*(100+0.01*Swell in Soil)/100).
What are the other ways to Calculate Loaded Volume?
Here are the different ways to Calculate Loaded Volume-
  • Loaded Volume=(Original volume of Soil/Load Factor)OpenImg
Can the Loaded Volume of Soil given Percent Swell be negative?
No, the Loaded Volume of Soil given Percent Swell, measured in Volume cannot be negative.
Which unit is used to measure Loaded Volume of Soil given Percent Swell?
Loaded Volume of Soil given Percent Swell is usually measured using the Cubic Meter[m³] for Volume. Cubic Centimeter[m³], Cubic Millimeter[m³], Liter[m³] are the few other units in which Loaded Volume of Soil given Percent Swell can be measured.