Late Finish Time evaluator uses Late Finish Time = Late Start Time+Duration of Activity to evaluate the Late Finish Time, Late Finish Time is the latest point in time when the scheduled activity can finish so as not to delay the project completion date or any constraint. Late Finish Time is denoted by LFT symbol.
How to evaluate Late Finish Time using this online evaluator? To use this online evaluator for Late Finish Time, enter Late Start Time (LST) & Duration of Activity (dur) and hit the calculate button.