Independent Float Formula

Fx Copy
LaTeX Copy
Independent Float is that portion of the total float within which an activity can be delayed to start without affecting the float of the preceding activities. Check FAQs
IF0=EFT-LST-tactivity
IF0 - Independent Float?EFT - Early Finish Time?LST - Late Start Time?tactivity - Activity Time?

Independent Float Example

With values
With units
Only example

Here is how the Independent Float equation looks like with Values.

Here is how the Independent Float equation looks like with Units.

Here is how the Independent Float equation looks like.

3Edit=46Edit-23Edit-20Edit
You are here -
HomeIcon Home » Category Engineering » Category Mechanical » Category Industrial Engineering » fx Independent Float

Independent Float Solution

Follow our step by step solution on how to calculate Independent Float?

FIRST Step Consider the formula
IF0=EFT-LST-tactivity
Next Step Substitute values of Variables
IF0=46d-23d-20d
Next Step Convert Units
IF0=4E+6s-2E+6s-1.7E+6s
Next Step Prepare to Evaluate
IF0=4E+6-2E+6-1.7E+6
Next Step Evaluate
IF0=259200s
LAST Step Convert to Output's Unit
IF0=3d

Independent Float Formula Elements

Variables
Independent Float
Independent Float is that portion of the total float within which an activity can be delayed to start without affecting the float of the preceding activities.
Symbol: IF0
Measurement: TimeUnit: d
Note: Value can be positive or negative.
Early Finish Time
Early Finish Time is the earliest point in time when the scheduled activity can complete.
Symbol: EFT
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Late Start Time
Late Start Time is the latest point in time when the scheduled activity can begin so as not to delay the project completion date or any constraint.
Symbol: LST
Measurement: TimeUnit: d
Note: Value should be greater than 0.
Activity Time
Activity time is the estimated task duration based on preceding logic and constraints.
Symbol: tactivity
Measurement: TimeUnit: d
Note: Value should be greater than 0.

Other formulas in Time Estimation category

​Go Early Finish Time
EFT=EST+S
​Go Expected Waiting Time for Customers in Queue
Wq=λaµ(µ-λa)
​Go Expected Waiting Time for Customers in System
Ws=1µ-λa
​Go Free Float
FF0=EFT-EST-tactivity

How to Evaluate Independent Float?

Independent Float evaluator uses Independent Float = Early Finish Time-Late Start Time-Activity Time to evaluate the Independent Float, Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities. Independent Float is denoted by IF0 symbol.

How to evaluate Independent Float using this online evaluator? To use this online evaluator for Independent Float, enter Early Finish Time (EFT), Late Start Time (LST) & Activity Time (tactivity) and hit the calculate button.

FAQs on Independent Float

What is the formula to find Independent Float?
The formula of Independent Float is expressed as Independent Float = Early Finish Time-Late Start Time-Activity Time. Here is an example- 3.5E-5 = 3974400-1987200-1728000.
How to calculate Independent Float?
With Early Finish Time (EFT), Late Start Time (LST) & Activity Time (tactivity) we can find Independent Float using the formula - Independent Float = Early Finish Time-Late Start Time-Activity Time.
Can the Independent Float be negative?
Yes, the Independent Float, measured in Time can be negative.
Which unit is used to measure Independent Float?
Independent Float is usually measured using the Day[d] for Time. Second[d], Millisecond[d], Microsecond[d] are the few other units in which Independent Float can be measured.