Batch Size given Non-productive Time in Turning Formula

Fx Copy
LaTeX Copy
Batch Size is the count of similar kinds of products to be manufactured. Check FAQs
Nb=ts+Nttst(NPT-tln-(tptn0))
Nb - Batch Size?ts - Basic Setup Time?Nt - Number of Tools Used?tst - Setup Time Per Tool?NPT - Non-Productive Time?tln - Loading And Unloading Time?tpt - Tool Positioning Time Per Operation?n0 - Number of Operations?

Batch Size given Non-productive Time in Turning Example

With values
With units
Only example

Here is how the Batch Size given Non-productive Time in Turning equation looks like with Values.

Here is how the Batch Size given Non-productive Time in Turning equation looks like with Units.

Here is how the Batch Size given Non-productive Time in Turning equation looks like.

2.9997Edit=20.5Edit+4Edit10Edit(28.169Edit-30Edit-(1.5Edit5Edit))
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Batch Size given Non-productive Time in Turning

Batch Size given Non-productive Time in Turning Solution

Follow our step by step solution on how to calculate Batch Size given Non-productive Time in Turning?

FIRST Step Consider the formula
Nb=ts+Nttst(NPT-tln-(tptn0))
Next Step Substitute values of Variables
Nb=20.5min+410min(28.169min-30s-(1.5min5))
Next Step Convert Units
Nb=1230s+4600s(1690.14s-30s-(90s5))
Next Step Prepare to Evaluate
Nb=1230+4600(1690.14-30-(905))
Next Step Evaluate
Nb=2.99965293271853
LAST Step Rounding Answer
Nb=2.9997

Batch Size given Non-productive Time in Turning Formula Elements

Variables
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Basic Setup Time
Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Setup Time Per Tool
Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Symbol: tst
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Non-Productive Time
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Symbol: NPT
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Loading And Unloading Time
Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Symbol: tln
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Tool Positioning Time Per Operation
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Symbol: tpt
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Operations
The Number of Operations is defined as the total number of operations done in a batch.
Symbol: n0
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.

Other formulas in Turning Operation category

​Go Diameter of Workpiece given Constant for Cylindrical Turning
d=KfπLcut
​Go Turning Length given Constant for Cylindrical Turning
Lcut=Kfπd

How to Evaluate Batch Size given Non-productive Time in Turning?

Batch Size given Non-productive Time in Turning evaluator uses Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))) to evaluate the Batch Size, The Batch Size given Non-productive Time in Turning is the count of similar kinds of products to be manufactured. Batch Size is denoted by Nb symbol.

How to evaluate Batch Size given Non-productive Time in Turning using this online evaluator? To use this online evaluator for Batch Size given Non-productive Time in Turning, enter Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) and hit the calculate button.

FAQs on Batch Size given Non-productive Time in Turning

What is the formula to find Batch Size given Non-productive Time in Turning?
The formula of Batch Size given Non-productive Time in Turning is expressed as Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))). Here is an example- 2.999653 = (1230+4*600)/((1690.14-30-(90*5))).
How to calculate Batch Size given Non-productive Time in Turning?
With Basic Setup Time (ts), Number of Tools Used (Nt), Setup Time Per Tool (tst), Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt) & Number of Operations (n0) we can find Batch Size given Non-productive Time in Turning using the formula - Batch Size = (Basic Setup Time+Number of Tools Used*Setup Time Per Tool)/((Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))).
Copied!