Batch Size given Average Production Time Formula

Fx Copy
LaTeX Copy
Batch Size is the count of similar kinds of products to be manufactured. Check FAQs
Nb=tcNttp-(ts+tm)
Nb - Batch Size?tc - Time to Change One Tool?Nt - Number of Tools Used?tp - Average Production Time?ts - Setup Time?tm - Machining Time?

Batch Size given Average Production Time Example

With values
With units
Only example

Here is how the Batch Size given Average Production Time equation looks like with Values.

Here is how the Batch Size given Average Production Time equation looks like with Units.

Here is how the Batch Size given Average Production Time equation looks like.

2Edit=300Edit3Edit550Edit-(54Edit+46Edit)
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Batch Size given Average Production Time

Batch Size given Average Production Time Solution

Follow our step by step solution on how to calculate Batch Size given Average Production Time?

FIRST Step Consider the formula
Nb=tcNttp-(ts+tm)
Next Step Substitute values of Variables
Nb=300s3550s-(54s+46s)
Next Step Prepare to Evaluate
Nb=3003550-(54+46)
LAST Step Evaluate
Nb=2

Batch Size given Average Production Time Formula Elements

Variables
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Time to Change One Tool
Time to Change One Tool is the measure of time it takes to change one tool during machining.
Symbol: tc
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Average Production Time
Average Production Time is the time taken to produce a single component out of a lot of produced batches.
Symbol: tp
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Setup Time
Setup Time of each component is the time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Machining Time
Machining Time is the time when a machine is actually processing something. Generally, machining time is the term used when there is a removal of unwanted material.
Symbol: tm
Measurement: TimeUnit: s
Note: Value should be greater than 0.

Other formulas in Average Production Time category

​Go Average Production Time of Each Component
tp=ts+tm+(NttcNb)
​Go Machining Time of Each Component given Average Production Time
tm=tp-ts-(NttcNb)
​Go Non-Productive Time for Each Component given Average Production Time
ts=tp-(tm+(NttcNb))
​Go Time for changing one Tool given Average Production Time
tc=(tp-(ts+tm))NbNt

How to Evaluate Batch Size given Average Production Time?

Batch Size given Average Production Time evaluator uses Batch Size = Time to Change One Tool*Number of Tools Used/(Average Production Time-(Setup Time+Machining Time)) to evaluate the Batch Size, The Batch Size given Average Production Time is a method to determine the maximum number of products that can be manufactured in a batch when the time it took to produce is limited. Batch Size is denoted by Nb symbol.

How to evaluate Batch Size given Average Production Time using this online evaluator? To use this online evaluator for Batch Size given Average Production Time, enter Time to Change One Tool (tc), Number of Tools Used (Nt), Average Production Time (tp), Setup Time (ts) & Machining Time (tm) and hit the calculate button.

FAQs on Batch Size given Average Production Time

What is the formula to find Batch Size given Average Production Time?
The formula of Batch Size given Average Production Time is expressed as Batch Size = Time to Change One Tool*Number of Tools Used/(Average Production Time-(Setup Time+Machining Time)). Here is an example- 1.778656 = 300*3/(550-(54+46)).
How to calculate Batch Size given Average Production Time?
With Time to Change One Tool (tc), Number of Tools Used (Nt), Average Production Time (tp), Setup Time (ts) & Machining Time (tm) we can find Batch Size given Average Production Time using the formula - Batch Size = Time to Change One Tool*Number of Tools Used/(Average Production Time-(Setup Time+Machining Time)).
Copied!