Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component. Check FAQs
ts=(NPT-tln-(tptn0))Nb-(Nttst)
ts - Basic Setup Time?NPT - Non-Productive Time?tln - Loading And Unloading Time?tpt - Tool Positioning Time Per Operation?n0 - Number of Operations?Nb - Batch Size?Nt - Number of Tools Used?tst - Setup Time Per Tool?

Basic Setup time given Non-productive Time in Turning Example

With values
With units
Only example

Here is how the Basic Setup time given Non-productive Time in Turning equation looks like with Values.

Here is how the Basic Setup time given Non-productive Time in Turning equation looks like with Units.

Here is how the Basic Setup time given Non-productive Time in Turning equation looks like.

20.507Edit=(28.169Edit-30Edit-(1.5Edit5Edit))3Edit-(4Edit10Edit)
You are here -
HomeIcon Home » Category Engineering » Category Production Engineering » Category Metal Machining » fx Basic Setup time given Non-productive Time in Turning

Basic Setup time given Non-productive Time in Turning Solution

Follow our step by step solution on how to calculate Basic Setup time given Non-productive Time in Turning?

FIRST Step Consider the formula
ts=(NPT-tln-(tptn0))Nb-(Nttst)
Next Step Substitute values of Variables
ts=(28.169min-30s-(1.5min5))3-(410min)
Next Step Convert Units
ts=(1690.14s-30s-(90s5))3-(4600s)
Next Step Prepare to Evaluate
ts=(1690.14-30-(905))3-(4600)
Next Step Evaluate
ts=1230.42s
LAST Step Convert to Output's Unit
ts=20.507min

Basic Setup time given Non-productive Time in Turning Formula Elements

Variables
Basic Setup Time
Basic Setup Time is the basic time required to load/unload the workpiece and position the tool for production for one component.
Symbol: ts
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Non-Productive Time
Non-Productive Time (NPT) refers to the time during which a machine is not actively engaged in producing parts.
Symbol: NPT
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Loading And Unloading Time
Loading And Unloading Time is the time required to load/unload the workpiece before the start of machine operation.
Symbol: tln
Measurement: TimeUnit: s
Note: Value should be greater than 0.
Tool Positioning Time Per Operation
Tool Positioning Time Per Operation is defined as the time taken in changing the tool before the start of operation.
Symbol: tpt
Measurement: TimeUnit: min
Note: Value should be greater than 0.
Number of Operations
The Number of Operations is defined as the total number of operations done in a batch.
Symbol: n0
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Batch Size
Batch Size is the count of similar kinds of products to be manufactured.
Symbol: Nb
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Number of Tools Used
The Number of Tools Used is the total number of tools used for manufacturing a batch of products.
Symbol: Nt
Measurement: NAUnit: Unitless
Note: Value should be greater than 0.
Setup Time Per Tool
Setup Time Per Tool is defined as the amount of time taken in setting up the tool while machining.
Symbol: tst
Measurement: TimeUnit: min
Note: Value should be greater than 0.

Other formulas in Turning Operation category

​Go Diameter of Workpiece given Constant for Cylindrical Turning
d=KfπLcut
​Go Turning Length given Constant for Cylindrical Turning
Lcut=Kfπd

How to Evaluate Basic Setup time given Non-productive Time in Turning?

Basic Setup time given Non-productive Time in Turning evaluator uses Basic Setup Time = (Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))*Batch Size-(Number of Tools Used*Setup Time Per Tool) to evaluate the Basic Setup Time, The Basic Setup time given Non-productive Time in Turning is the basic time required to load/unload the workpiece and position the tool for production for one component. Basic Setup Time is denoted by ts symbol.

How to evaluate Basic Setup time given Non-productive Time in Turning using this online evaluator? To use this online evaluator for Basic Setup time given Non-productive Time in Turning, enter Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt), Number of Operations (n0), Batch Size (Nb), Number of Tools Used (Nt) & Setup Time Per Tool (tst) and hit the calculate button.

FAQs on Basic Setup time given Non-productive Time in Turning

What is the formula to find Basic Setup time given Non-productive Time in Turning?
The formula of Basic Setup time given Non-productive Time in Turning is expressed as Basic Setup Time = (Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))*Batch Size-(Number of Tools Used*Setup Time Per Tool). Here is an example- 0.341783 = (1690.14-30-(90*5))*3-(4*600).
How to calculate Basic Setup time given Non-productive Time in Turning?
With Non-Productive Time (NPT), Loading And Unloading Time (tln), Tool Positioning Time Per Operation (tpt), Number of Operations (n0), Batch Size (Nb), Number of Tools Used (Nt) & Setup Time Per Tool (tst) we can find Basic Setup time given Non-productive Time in Turning using the formula - Basic Setup Time = (Non-Productive Time-Loading And Unloading Time-(Tool Positioning Time Per Operation*Number of Operations))*Batch Size-(Number of Tools Used*Setup Time Per Tool).
Can the Basic Setup time given Non-productive Time in Turning be negative?
No, the Basic Setup time given Non-productive Time in Turning, measured in Time cannot be negative.
Which unit is used to measure Basic Setup time given Non-productive Time in Turning?
Basic Setup time given Non-productive Time in Turning is usually measured using the Minute[min] for Time. Second[min], Millisecond[min], Microsecond[min] are the few other units in which Basic Setup time given Non-productive Time in Turning can be measured.
Copied!