Late Start Time is the latest point in time when the scheduled activity can begin so as not to delay the project completion date or any constraint. And is denoted by LST. Late Start Time is usually measured using the Day for Time. Note that the value of Late Start Time is always positive.
Industrial Engineering formulas that make use of Late Start Time
f
x
Independent Float
Go
f
x
Late Finish Time
Go
f
x
Total Float given Start Time
Go
FAQ
What is the Late Start Time?
Late Start Time is the latest point in time when the scheduled activity can begin so as not to delay the project completion date or any constraint. Late Start Time is usually measured using the Day for Time. Note that the value of Late Start Time is always positive.
Can the Late Start Time be negative?
No, the Late Start Time, measured in Time cannot be negative.
What unit is used to measure Late Start Time?
Late Start Time is usually measured using the Day[d] for Time. Second[d], Millisecond[d], Microsecond[d] are the few other units in which Late Start Time can be measured.