The Falling rate drying time is the time taken for drying operation in the falling rate period. And is denoted by t
f
. Falling Rate Drying Time is usually measured using the Second for Time. Note that the value of Falling Rate Drying Time is always positive.
Formulas to find Falling Rate Drying Time in Falling Rate Drying Period
f
x
Falling Rate Drying Time from Critical to Final Moisture
Go
f
x
Falling Rate Drying Time from Critical to Final Weight of Moisture
Go
f
x
Falling Rate Drying Time from Initial to Final Moisture
Go
f
x
Falling Rate Drying Time from Initial to Final Weight of Moisture
Go
Falling Rate Drying Period formulas that make use of Falling Rate Drying Time
f
x
Drying Surface Area based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Drying Surface Area based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Dry Weight of Solid based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Final Moisture Content based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Final Weight of Moisture based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Drying Surface Area based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Drying Surface Area based on Initial to Final Weight of Moisture for Falling Rate Period
Go
f
x
Dry Weight of Solid based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Final Moisture Content based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Final Weight of Moisture based on Initial to Final Weight of Moisture for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Initial to Final Weight of Moisture for Falling Rate Period
Go
List of variables in Falling Rate Drying Period formulas
f
x
Dry Weight of Solid
Go
f
x
Drying Surface Area
Go
f
x
Critical Moisture Content
Go
f
x
Equilibrium Moisture Content
Go
f
x
Rate of Constant Drying Period
Go
f
x
Final Moisture Content for Falling Rate Period
Go
f
x
Critical Weight of Moisture
Go
f
x
Equilibrium Weight of Moisture
Go
f
x
Final Weight of Moisture for Falling Rate Period
Go
f
x
Initial Moisture Content for Falling Rate Period
Go
f
x
Initial Weight of Moisture for Falling Rate Period
Go
FAQ
What is the Falling Rate Drying Time?
The Falling rate drying time is the time taken for drying operation in the falling rate period. Falling Rate Drying Time is usually measured using the Second for Time. Note that the value of Falling Rate Drying Time is always positive.
Can the Falling Rate Drying Time be negative?
No, the Falling Rate Drying Time, measured in Time cannot be negative.
What unit is used to measure Falling Rate Drying Time?
Falling Rate Drying Time is usually measured using the Second[s] for Time. Millisecond[s], Microsecond[s], Nanosecond[s] are the few other units in which Falling Rate Drying Time can be measured.