FormulaDen.com
Physics
Chemistry
Math
Chemical Engineering
Civil
Electrical
Electronics
Electronics and Instrumentation
Materials Science
Mechanical
Production Engineering
Financial
Health
You are here
-
Home
»
Engineering
»
Chemical Engineering
»
Mass Transfer Operations
Falling Rate Drying Time in Drying Formulas
The Falling rate drying time is the time taken for drying operation in the falling rate period. And is denoted by t
f
. Falling Rate Drying Time is usually measured using the Second for Time. Note that the value of Falling Rate Drying Time is always positive.
Formulas to find Falling Rate Drying Time in Drying
f
x
Falling Rate Drying Time from Critical to Final Moisture
Go
f
x
Falling Rate Drying Time from Critical to Final Weight of Moisture
Go
f
x
Falling Rate Drying Time from Initial to Final Moisture
Go
f
x
Falling Rate Drying Time from Initial to Final Weight of Moisture
Go
f
x
Falling Drying Time based on Constant Drying Time and Total Drying Time
Go
Drying formulas that make use of Falling Rate Drying Time
f
x
Drying Surface Area based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Drying Surface Area based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Dry Weight of Solid based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Final Moisture Content based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Final Weight of Moisture based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Critical to Final Moisture Content for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Critical to Final Weight of Moisture for Falling Rate Period
Go
f
x
Drying Surface Area based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Drying Surface Area based on Initial to Final Weight of Moisture for Falling Rate Period
Go
f
x
Dry Weight of Solid based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Final Moisture Content based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Final Weight of Moisture based on Initial to Final Weight of Moisture for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Initial to Final Moisture Content for Falling Rate Period
Go
f
x
Rate of Constant Drying Period based on Initial to Final Weight of Moisture for Falling Rate Period
Go
f
x
Total Drying Time based on Constant Drying Time and Falling Drying Time
Go
f
x
Constant Drying Time based on Total Drying Time and Falling Drying Time
Go
List of variables in Drying formulas
f
x
Dry Weight of Solid
Go
f
x
Drying Surface Area
Go
f
x
Critical Moisture Content
Go
f
x
Equilibrium Moisture Content
Go
f
x
Rate of Constant Drying Period
Go
f
x
Final Moisture Content for Falling Rate Period
Go
f
x
Critical Weight of Moisture
Go
f
x
Equilibrium Weight of Moisture
Go
f
x
Final Weight of Moisture for Falling Rate Period
Go
f
x
Initial Moisture Content for Falling Rate Period
Go
f
x
Initial Weight of Moisture for Falling Rate Period
Go
f
x
Total Drying Time
Go
f
x
Constant Rate Drying Time
Go
FAQ
What is the Falling Rate Drying Time?
The Falling rate drying time is the time taken for drying operation in the falling rate period. Falling Rate Drying Time is usually measured using the Second for Time. Note that the value of Falling Rate Drying Time is always positive.
Can the Falling Rate Drying Time be negative?
No, the Falling Rate Drying Time, measured in Time cannot be negative.
What unit is used to measure Falling Rate Drying Time?
Falling Rate Drying Time is usually measured using the Second[s] for Time. Millisecond[s], Microsecond[s], Nanosecond[s] are the few other units in which Falling Rate Drying Time can be measured.
Let Others Know
✖
Facebook
Twitter
Reddit
LinkedIn
Email
WhatsApp
Copied!