Early Start Time is the earliest point in time when the scheduled activity can begin. And is denoted by EST. Early Start Time is usually measured using the Day for Time. Note that the value of Early Start Time is always positive.
Industrial Engineering formulas that make use of Early Start Time
f
x
Early Finish Time
Go
f
x
Free Float
Go
f
x
Total Float
Go
f
x
Total Float given Start Time
Go
FAQ
What is the Early Start Time?
Early Start Time is the earliest point in time when the scheduled activity can begin. Early Start Time is usually measured using the Day for Time. Note that the value of Early Start Time is always positive.
Can the Early Start Time be negative?
No, the Early Start Time, measured in Time cannot be negative.
What unit is used to measure Early Start Time?
Early Start Time is usually measured using the Day[d] for Time. Second[d], Millisecond[d], Microsecond[d] are the few other units in which Early Start Time can be measured.
Let Others Know
✖